{"id":34982,"date":"2026-08-27T16:09:10","date_gmt":"2026-08-27T14:09:10","guid":{"rendered":"https:\/\/www.soletanche.pl\/?post_type=avada_portfolio&p=34982"},"modified":"2026-09-21T17:25:56","modified_gmt":"2026-09-21T15:25:56","slug":"krakow-fast-tram-krakow","status":"publish","type":"avada_portfolio","link":"https:\/\/www.soletanche.pl\/en\/offer-portfolio\/krakow-fast-tram-krakow\/","title":{"rendered":"Krakow Fast Tram, Krakow"},"content":{"rendered":"

Project description<\/div><\/h2><\/div>

Krakow Fast Tram \u2013 Stage IV is a double-track tram line connecting two existing tram lines in the northern part of Krakow, in District III Pr\u0105dnik Czerwony and District XV Mistrzejowice. The total length of the tram line is 4.5 km, including 1.23 km of underground tunnel. The project has contributed to reducing road traffic and improving air quality in central Krakow, as well as reducing greenhouse gas emissions by providing residents with alternative transport options.<\/p>\n<\/div>

<\/div>
<\/div>
<\/div>

Soletanche Polska scope of works<\/div><\/h3><\/div>

Soletanche Polska\u2019s scope of works included the construction of diaphragm walls along the tram tunnel section and at the underground passenger stations \u2013 Rondo Polsadu and Rondo M\u0142y\u0144skie. The total length of the diaphragm walls constructed was approximately 2.5 km, with a maximum depth of 21 metres.<\/p>\n<\/div>

<\/span><\/div>
<\/div><\/div><\/div>

Project location:<\/p>\n

Krakow, Poland<\/span><\/b><\/p>\n<\/div>

<\/div>
<\/div><\/div>
<\/div>

Investor:<\/span><\/p>\n

City of Krakow<\/span><\/b><\/p>\n<\/div>

<\/div>
<\/div><\/div>
<\/div>

General Contractor:<\/p>\n

G\u00fclermak<\/span><\/b><\/p>\n<\/div>

<\/div>
<\/div><\/div>
<\/div>

Number of tracks:<\/span><\/p>\n

2<\/span><\/b><\/p>\n<\/div>

<\/div>
<\/div><\/div>
<\/div>

Number of stops:<\/span><\/p>\n

10<\/span><\/b><\/p>\n<\/div>

<\/div>
<\/div><\/div>
<\/div>
<\/div><\/div><\/div>

The diaphragm walls were designed to perform various functions. Primarily, they serve as the permanent lining of the underground tunnel and as permanent structural elements of the underground stations and their access points. In some locations, they also served as temporary retaining structures, securing the excavation during construction works.<\/p>\n<\/div>

\n

The construction of Stage IV of the Krakow Fast Tram was a complex undertaking due to the location of the project within a residential area, in the immediate vicinity of numerous office buildings, shops and extensive transport infrastructure carrying heavy traffic.
\nFoundation works were carried out, among other locations, beneath the operational General Pilot Mateusz I\u017cycki Flyover, which significantly restricted the available headroom and thus the space required to safely operate large and heavy construction equipment. The clearance between ground level and the underside of the flyover girders was only 7 metres. In order to construct diaphragm walls 80 centimetres thick and up to 21 metres deep in this location, it was necessary to bring in specialised equipment from France and Germany.
\nThroughout the works, the flyover and nearby buildings were monitored using a specialised inclinometric monitoring system. This enabled continuous monitoring of the condition and behaviour of the structures, as well as the impact of the construction works on the surrounding infrastructure and its environment.<\/p>\n<\/div>\n<\/div>

Technologies applied<\/div><\/h3><\/div>
    \n
  • diaphragm walls with temporary propping,<\/li>\n
  • barrettes,<\/li>\n
  • cut-off walls,<\/li>\n
  • ground anchors.<\/li>\n<\/ul>\n<\/div>